Thursday 20th April 2006
|
|
| |
|
| Wednesday 10th May 2006
|
![]() |
![]() |
|
| |
|
Tuesday 16th May 2006 Work on the site is progressing rapidly and the shape of the New Dingwall Academy is clear to see from the excavations.
|
|
Thursday 18th May 2006 What a difference two days make, most of the turf has been scraped away and the contractors are moving in for the duration.
|
|
| |
|
Tuesday 23rdMay 2006 The outline of the New Academy is now plain to see. Most of the top soil and clay has been removed and is now being replaced by layers of hardcore.
|
|
| |
Friday 26th May 2006 A busy site shown below with top soil being removed and hard core being delivered. Also a core sample being taken of the subsoil all the way down to the bed rock six metres below.
|
| |
Wednesday 31st May 2006 Click the link below to see the colour options for the New Academy. Please
note: The latest panorama photograph, taken this morning, shows how the site is progressing.
|
| |
|